Cabinet design is locked in, most of the finishes have been chosen, some appliances have been purchased.
Electrical hardware, load center, boxes and wire have been aquired. Have plan for labor which involves friends.
HVAC contractor has been chosen and scope of work has been approved.
Plumbing rough in is still up in the air but have some leads that we need to work on (labor and materials).
We are very very close to cranking up again................

All old the brick from the garage wall and short wall from old house corner and media room fireplace chimney has been removed.

Brick from the old garage wall is currently in a huge pile outside of the house. The plan is to use as fill in this side's landscaping/walkway development.

Just to shown current firplace and how it appears today. Please note we had a fire and it works great. I looked on the internet for fireplaces in kitchens and have not found one like this yet (thinking it is very unique). I have also started looking into how to build in a crane for kettles (if cooking in fireplace) that could be removable if desired, the thought of using the fireplace for cooking at times appeals to us.